A320 LATEST......
We have written to GRAHAM Construction to open communications and have received a positive response back the same day...a good sign we think the content of their response is below.
Good afternoon Bob,
Thank you for reaching out and expressing your concerns about the road scheme, particularly the Otter Roundabout / J10.
I have forwarded your letter on to our contracts manager within GRAHAM for review.
I thought in the interest of establishing a collaborative relationship with the ONF, I would respond to you with my direct email address, I hope this settles your doubts regarding our commitment to yourself and the rest of your community. Going forward I would happily be the voice of our road scheme, and once our construction programme is finalised, I would be pleased to have an informal / formal meeting with yourself to run through our plans with you.
Now I know there seems to be unrest in the community regarding J10, especially with the residents of Ottershaw, and I cannot promise that an agreeable solution can be met. But what I can guarantee is that I will communicate with yourselves as best I can, and from this, I hope a solid relationship can be created over the months to come.
We are in the process of securing a site compound for our satellite offices and finalising a programme of works with our client, with works advertised to start ‘Spring 2025’, this is looking likely to be the start of April. Our first works location will be the St Peters Roundabout, where we have begun our site clearance works.
Have a good weekend Bob and I will be in touch soon regarding our works going forward.
I would appreciate if when passing on my details you direct anyone to civilscustomerrelations@graham.co.uk, where I / my team will respond within 5 working days. For yourself, please feel free to email me direct.
Kind regards
Harry Knapp
Stakeholder & Community Engagement Officer| Civil Engineering Division